N25 Bandon/Sarsfield Interchanges Upgrade
Progress Update – 1st November 2011
The section of the N25 South Ring Road between Bandon Road Roundabout and Sarsfield Road Roundabout was reopened to traffic at 8p.m. on Monday 31st October, 2011, almost 12 hours ahead of schedule.
Traffic had been diverted from this section of the South Ring Road over the Bank Holiday weekend to facilitate demolition of the pedestrian bridges at Sarsfield Road Roundabout and at Bandon Road Roundabout. The traffic diversion was put in place at 9p.m. on Friday 28th October, 2011 and demolition works continued on a 24 hour basis over the Bank Holiday weekend in order to ensure that the road would be reopened to traffic for commuters as quickly as possible.
The main contract for the N25 Bandon/Sarsfield Interchanges Upgrade is being carried out by SIAC Construction Ltd. The demolition works were sub-contracted to a specialist demolition firm, Loftus Civil Engineering Ltd. in partnership with Michael Harrington Plant Hire Bantry Ltd.
The initial focus was on the Bandon Road footbridge with works there getting underway at around 11p.m. on Friday 28th October, 2011.